Sprint 0

Duration

2 October 2023 to 8 October 2023

Attendees

Team Members

  • Bruna Simões
    • Product Owner
  • Filipe Silveira
  • Mariana Andrade
  • Mateus Almeida
  • Vicente Barros
    • Scrum Master

Sprint Goal

Setup the necessary environments to begin development of the project and write the initial Product Backlog,

Product Backlog Items (PBI)

Planned PBI

  • MM-1 Setup Github Organization
  • MM-2 Plan Team roles
  • MM-3 Create initial User Stories
  • MM-5 Create Functional Requirements
  • MM-10 Create rough sketch of database
  • MM-11 Create rough sketch of the architecture
  • MM-18 Create Software mockup
  • MM-32 Create Docusaurus

Completed PBI

  • MM-1 Setup Github Organization
  • MM-2 Plan Team roles
  • MM-3 Create initial User Stories
  • MM-5 Create Functional Requirements
  • MM-18 Create Software mockup
  • MM-32 Create Docusaurus

Incomplete PBI

  • MM-10 Create rough sketch of database
  • MM-11 Create rough sketch of the architecture

Demonstrations

As development of the product has not yet begun, the demonstration only encompassed the definition of key actors, "Definition of Ready" and "Definition of Done", which are as follows:

Key actors

  • Consumer, which wants to buy handmade items
  • Seller, which seeks an intuitive and easy-to-use platform to sell their items

Definition of Ready

  • Small
  • Independent
  • Testable
  • Estimated Cost

Definition of Done

  • Must pass all the tests
  • Must pass the quality Gates of Sonarcloud
  • Must be peer Reviewed by another member of the team
  • Must comply with the acceptance criteria
  • Must be documented in Docussaurus

Sprint Review

With this being the very first sprint in mind, it can be concluded that it was completed successfully, with all members dutifully completing their assigned tasks and goals. The next steps will be taken as to ensure the swift beginning of development of the product, such as beginning development of the front-end, back-end and API of said product.

Next Sprint Planning

Items for Sprint 1:

  • MM-7 View Catalog
  • MM-19 Search a Product
  • MM-22 Filter Products
  • MM-54 View Product
  • MM-36 Announce a Product
  • MM-43 Change Product Attributes
  • MM-41 Delete Product
  • MM-56 Create brand logo
  • MM-10 Create rough sketch of database
  • MM-11 Create rough sketch of architecture Changes to Product Backlog:
  • Backlog was refined and prioritized according to new insights and the outlook of the next sprint